Step-By-Step Commissioning Guide - ABB PFEA 111 User Manual

Web tension systems with tension electronics
Table of Contents

Advertisement

Tension Electronics PFEA111/112, User Manual
Chapter 3 Commissioning

3.6 Step-by-step Commissioning Guide

3-4
Step
Measurement
1
Check that the main supply voltage is switched off.
2
Check all cabling according to the cable diagrams.
3
Check the supply voltage
DIN-rail mounted IP20-unit (unsealed)
Nominal 24 V DC, Working range 18 - 36 V DC, X1:1-2
Wall mounted IP65-unit (NEMA 4)
85 - 264 V AC (100 V - 15% to 240 V + 10%), 45-65 Hz, X9:1-2
Nominal 24 V DC, Working range 18 - 36 V DC, X1:1-2
4
Perform basic settings (if necessary)
5
Perform setup:
Fast setup
Complete setup
6
Check load cell signal polarity
7
Check load cell function
See section
Appendix
B, C, D, E, F
or G
3.7
3.7
3.8
3.11
3.9
3.10
3BSE029380R0101 Rev C