3.6 INSPECTION

3.6.1 BEFORE POWER START-UP
1.
Ensure the power supply specification is correct.
2.
Ensure electric cables and connectors are appropriating based on the local safety
regulations.
3.
Ensure connections between the machine and grounding terminals are correct.
4.
Ensure the current-fault breaker required by the local safety regulations is installed on the
power supply side.
5.
Ensure all the temporary fastening equipment used during the transportation process is
removed.
6.
Ensure there is no loose part on the working table.
7.
Ensure there is no loose part on the folding guard.
8.
Ensure all the fixing studs are fastened properly.
9.
Secure nuts, bolts, locks, and other parts needed to be secured.
10. Ensure the hydraulic, pneumatic, and cutting coolant systems are connected properly.
11. Ensure safety-guarding shields and doors are in a good condition.
12. Ensure the hydraulic oil, lubricant, and cutting coolant are filled up to the required level.
13. Ensure all the over-travel limit switch are working.
14. Ensure tension of the spindle driver's belt is appropriate.
15. Ensure there is no unexpected person or substance around the machine before
starting up the machine.
16. Read manuals carefully and ensure you understand all the safety instructions and
operating procedures before starting up the machine.
V-1 KNEE MILL GENERAL MANUAL
CH3-14
KRDM24C0 V4.0S

Hide quick links: