Commissioning

Checks prior to commissioning

The following points must be checked before commissioning
the device:
• Correct wiring in accordance with Electrical connections
on page 28.
• Correct grounding of the sensor.
• The ambient conditions must meet the requirements set
out in the specification.
• The power supply must meet the requirements set out on
the name plate.

Parameterization of the device

The FEM630 can be commissioned and operated via the
integrated LCD indicator (option, see Parameterization via
the menu function Easy Setup on page 55).
Alternatively, the FEM630 can also be commissioned and
operated via ABB Asset Vision Basic (FET6xx DTM).
Parameterization with the optional LCD indicator
1
Local operating interface
2
Coupler connectors for LCD indicator
3
LCD indicator
Figure 63 Optional LCD indicator
For devices without LCD indicator, an optional LCD indicator
for parameterization can be connected.
Parameterization via the local operating interface
DANGER
Explosion hazard
Risk of explosion during operation of the device with
open terminal box!
• Only perform parameterization of the device via the
local operating interface outside potentially explosive
atmospheres!
A PC / Notebook and the USB interface cable are needed to
configure the device via the device local operating interface.
By combining the HART-DTM and the softwareflow available
at www.abb.com/ABB AssetVision, all parameters can also be
set without a fieldbus connection.
1
Local operating interface
2
USB-interface cable
3
PC / Notebook
Figure 64 Connection to the local operating interface
1
Open device terminal box.
2
Connect programming plug to the local operating
interface of the device.
3
Insert USB interface cable into a free USB female
connector on the PC / notebook.
4 Switch on the device power supply.
5
Start ABB AssetVision and perform the parameterization
of the equipment.
Detailed information on operating the software is available in
the relevant operating instructions and the DTM online help.