Users Manual

Cutout Test

Fluke Calibration recommends you do a minimum of one
cutout test in 6 months. To do a cutout test:
1. Push .
2. Set the setpoint temperature to 400 °C and let the
furnace temperature become stable.
3. Push .
4. Push .
5. Push the softkey below TEMP SETUP.
6. Push the softkey below CUTOUT.
7. Set the soft cutout to 300 °C.
The cutout indicator on the front panel illuminates and
the furnace stops the heat cycle. If the cutout does not
stop the heat cycle, the Product must be repaired.
8. Set the soft cutout temperature to 1240 °C.
60

How to Clean the Product

Clean the Product surfaces with a damp cloth and mild
detergent. Make sure liquids do not go into the Product.
Before you clean or decontaminate the Product
with a procedure not recommended by Fluke
Calibration, speak with a service center associate
for more information.

Furnace Calibration

The furnace calibration procedure in this manual is a
general guideline. Each calibration laboratory must write a
procedure for their calibration equipment and quality
program. Do an uncertainty analysis with the laboratory
equipment and environment.
To get answers to furnace calibration questions,
talk to a Fluke Calibration associate. See the How
to Contact Fluke section.
 Warning
To prevent possible electrical shock, fire, or
personal injury, have an approved technician
calibrate the Product.
A technician who does the furnace calibration procedure
must know the data in this manual.