Installation
3.
Remove the three bolts securing the right side shipping bracket to the cabinet and three bolts securing
the bracket to the pallet (see Figure 4-2). Remove the right side shipping bracket.
Front Door
Figure 4-2. Removing the ISBM Section Right Side Shipping Bracket
4.
Using a forklift (see the caution statement at the beginning of this procedure), raise the cabinet until the
cabinet bottom clears the pallet by approximately 3 mm (1/8").
5.
Pull the pallet from under the cabinet. Discard or recycle the pallet and shipping brackets in a responsible
manner.
6.
Carefully lower the cabinet until the cabinet base contacts the floor.
7 .
If installing an FI-UPM, go to paragraph 4-5. If installing a battery system, go to paragraph 4-6. Otherwise,
go to paragraph 4-7 to complete the wiring of the UPS.
®
4-4
Eaton
Power Xpert
ISBM Removable
Front Panels
Pallet
Left Side
Shipping Bracket
®
9395P-300 (300kVA, 300kW) UPS Installation and Operation Manual P-164000563—Rev 04 www.eaton.com/powerquality
Shipping Bracket
Bolts
Shipping Bracket
Bolts