checks the grid voltage, measures the insulation resistance of the pho-
checks. During the preliminary checks on the parallel connection with the
If the outcome of the preliminary checks on the grid parallel is positive, the
inverter connects to the grid and starts to export power to the grid. The
To address any problems that may occur during the initial stages of operation of the system
updates in the download area of the website www.abb.com/solarinverters or at https://regi-
stration.abbsolarinverters.com (instructions for registering on the website and updating the
test the meter and the battery working and it will reboot at the
- 110 -
7 - Operation
Need help?
Do you have a question about the REACT 2 Series and is the answer not in the manual?
Questions and answers