802-9074.9 • INSTALLATION AND OPERATING INSTRUCTIONS • NXPLUS C Wind • Revision 05
Fig. 58:
Bolted joints for panel interconnection
Mount the panel link
nut-and-washer assemblies
Fig. 59:
Panel link, mounted
Check the reference dimension K1 between the bushings (see page 72, "Assembling the
busbars").
Remove cable compartment covers and operating mechanism covers.
ATTENTION!
After removal, the cable compartment and operating mechanism covers must be mounted on
the same panels again.
Write the corresponding panels numbers on all covers after removal.
Approach all other panels one after the other, align them and bolt the alignment brackets
and the frames together.
between the two panels with two bolts M8x45 (saucer-head) and
.
Felt strips, pre-assembled at the factory
Screw M5x16, thread-ridging
Bolt M8x20, with nut-and-washer assembly
Panel link
Bolt M8x45 and nut-and washer assembly
Installation
71/172