Siemens NXPLUS C Installation And Operating Instructions Manual page 110

Medium-voltage switchgear/wind fixed mounted circuit-breaker switchgear up to 36 kv, extendable
Table of Contents

Advertisement

Installation
110/172
Laying the current transformer leads and wires for the capacitive voltage detecting
system in the right-hand wiring duct
Lay overlong current transformer leads in meanders.
Fig. 101: Current transformer leads laid in meanders in the right-hand wiring duct
Laying wire groups keeping the maximum possible distance between them and tight on the earthed plate.
Fig. 102: Wire groups laid in the right-hand wiring duct keeping the maximum possible
distance between them
Revision 05 • INSTALLATION AND OPERATING INSTRUCTIONS • NXPLUS C Wind • 802-9074.9
Current transformer lead
Wire for capacitive voltage detecting system
Current transformer lead
Laying wire groups keeping the maximum possible distance
between them
Wire for capacitive voltage detecting system

Advertisement