Test Operation With Auxiliary Voltage (Motor Operating Mechanism) - Siemens NXPLUS C Installation And Operating Instructions Manual

Medium-voltage switchgear/wind fixed mounted circuit-breaker switchgear up to 36 kv, extendable
Table of Contents

Advertisement

Operation
Circuit-breaker with
stored-energy mechanism
Circuit-breaker with
spring-operated
mechanism
134/172
ATTENTION!
If the retaining screw of the striker is not shifted back from position A to position B after the
test operation without auxiliary voltage, the undervoltage release will not function.
After the test operation without auxiliary voltage, shift the retaining screw of the striker
back from position A to position B.
Shift the retaining screw of the striker from position A to B to activate the undervoltage
release.
20.4

Test operation with auxiliary voltage (motor operating mechanism)

Switch on the supply voltage.
The motor operating mechanism starts up and charges the closing spring.
r
Check whether the "closing spring charged" indication appears.
Close the circuit-breaker.
The closing spring is recharged automatically.
r
Check whether the position indication "circuit-breaker CLOSED" appears.
Open the circuit-breaker.
Check whether the position indication "circuit-breaker OPEN" appears.
Switch on the supply voltage.
The motor operating mechanism starts up, charges the closing spring and opens
r
automatically.
Check whether the position indication "circuit-breaker CLOSED" appears.
Open the circuit-breaker.
Check whether the position indication "circuit-breaker OPEN" appears.
Revision 05 • INSTALLATION AND OPERATING INSTRUCTIONS • NXPLUS C Wind • 802-9074.9