Fig. 89:
Disconnector panel, ring-main panel: Phase
sequence of bushings in the cable compartment
Earth the feeder.
Undo the fixing screws of the cable compartment cover.
Lift the cable compartment cover and remove it to the front.
Remove the pressure-resistant floor cover (see page 93, "Removing the pressure-resistant
floor cover").
Cut rubber sleeves to size (see page 96, "Cutting the rubber sleeves to size").
ATTENTION!
Surfaces of high-quality joints can easily be damaged by incorrect handling.
Observe extreme cleanliness.
ATTENTION!
Cable plugs can easily be damaged by incorrect handling.
Make sure that the cable T-plugs are mounted on the cable ends by instructed personnel.
Make sure that mounted cable plugs are not bended or twisted.
ATTENTION!
Do not operate the outside-cone bushings of the cable compartment without cable T-plugs.
If no cables are connected and the panel is to be energized, the outside-cone bushings
must be closed in a surge-proof way.
Mount the surge-proof end cap for bushing type "C" (with bolted contact M16),
type 8DX1488.