Normal System Indications During Turn-Up

As the system powers up and begins normal operation, the indicators on the front of
all installed Output modules should go through the following sequence:
The POWER indicator turns green when power is applied to the unit and stays
green.
The STATUS indicator blinks green and amber for approximately 10 to 15
seconds and then stays green.
The SOURCE indicator turns green for source clock, amber for not source
clocks, and off for non-existent clocks.
The POWER indicator and both –48/60 VDC indicators on the installed Buffer
modules should turn green and stay green.
After Turn-Up
After completing the turn up procedures:
Assign a System Administrator and any additional users to the system using the
procedures in
Make any required changes to the factory default configuration settings as
described in
Complete the commissioning tests in
to ensure that the system is functioning properly.
Refer to
Chapter 5, Maintenance and Troubleshooting
alarms that might occur.
This completes the turn-up procedures. See
the
SSU-2000e, for instructions on connecting to the SSU-2000e and assigning a
system administrator and additional users (system is password protected). Then
refer to
Chapter 4, Commissioning the
the system is functioning properly, or to
Troubleshooting, to clear any persistent system alarms.
12713140-002-2 Revision E – October 2006
Adding An Administrator
Chapter 3, Provisioning and Operating the
Chapter 2 Installing the SSU-2000e
User, on page 95.
SSU-2000e.
Chapter 4, Commissioning the
to clear any system
Chapter 3, Provisioning and Operating
SSU-2000e, for test procedures to ensure
Chapter 5, Maintenance and
After Turn-Up
SSU-2000e,