Chapter 4 Commissioning the SSU-2000e

Commissioning Test Data Sheet

Commissioning Test Data Sheet
Complete the following test data sheet as an indicator of operational readiness of
the SSU-2000e.
Table 4-2. Commissioning Test Data Sheet - SSU
Ethernet communications
EIA-232 Port A communications
EIA-232 Port B communications
EIA-232 Port C communications (on front of
Communications module)
MINOR Alarms
MAJOR Alarms
CRITICAL Alarms
Reference Signals and Selection
Clock Section
Output Section
System Stability and Accuracy (optional)
Commissioning the SDU 2000e
The SDU-2000e expansion chassis commissioning tests are checklist-based
operational tests performed by field engineers at the installation site after
completing installation, system power-up, and provisioning to verify that the system
is correctly installed, configured, and operating properly. After testing and
verification of system functionality, the system is ready to be placed in service.
124 SSU-2000e User's Guide
Test
Pass
Fail