Indicators; Power Supply Testing; Communications - GE F650 User Manual

Grid solutions digital bay controller
Hide thumbs Also See for F650:
Table of Contents

Advertisement

CHAPTER 6: COMMISSIONING

6.5 Indicators

Feed the relay and verify that when commanding a LED reset operation, all LED indicators light up and they are turned off
when pressing the ESC key for more than 3 seconds.

6.6 Power supply testing

Feed the relay with the minimum and maximum voltage. For each voltage value, verify that the alarm relay is activated
when there is voltage, and it is deactivated when there is no feed. If the power supply source incorporates AC feed, this test
is also performed for VAC.
If the relay incorporates a redundant power supply, these tests shall be performed on both power supplies.
Voltage values to be applied are the ones indicated below according to the relay model:
NOTE: Codes HIR and LOR correspond to a redundant power supply

6.7 Communications

Verify that available communication ports allow communication with the relay.
Ports to be checked are as follows:
Front:RS232
Rear:2 x RS485, 2 x Fiber Optic - Serial, 2 x Fiber Optic - Ethernet, 1 x RJ45 - Ethernet .
A computer with EnerVista 650 Setup software and an appropriate connector must be used.
GEK-113000-AF
SUPPLY
V min.
HI/HIR
110-250 Vdc
88 Vdc
120-230 Vac
96 Vac
LO/LOR
24-48 Vdc
19.2 Vdc
F650 DIGITAL BAY CONTROLLER
V max.
300 Vdc
250 Vac
57.6 Vdc
6.5 INDICATORS
6-5

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents