DLP-L53 Turning On and Verifying DC Office Power on the NCS2002Shelf

Prerequisite Procedures
Required/As Needed
Onsite/Remote
Security Level
Caution
Do not apply power to the shelf until you complete all the installation steps.
To ensure safety of personnel and equipment, do not connect any power cables into the power module
Warning
until the module is completely installed into the chassis. Statement 389
To reduce the risk of electric shock, switch on the power only after the power cord is completely
Warning
installed into the power module. Statement 390
Procedure
Step 1
To power up the node, insert the fuse into the fuse position according to site practice. The fuse rating must
not exceed 15A in case of AC power.
Step 2
If the NCS 2002 does not power up, check the voltage at the power source using a voltmeter. The voltage
should be 100 to 240 VAC +/-10 percent.
Step 3
Return to your originating procedure (NTP).
DLP-L53 Turning On and Verifying DC Office Power on the NCS2002Shelf
Purpose
Cisco NCS 2000 Series Hardware Installation Guide
92
Connecting Power and Ground
• Connect the chassis to the office ground. For
detailed instructions on how to ground the
chassis, refer to the
Electrostatic Discharge and
Grounding Guide for Cisco NCS 2000 Series
NTP-L30 Opening and Removing the Standard
Door of the NCS 2002 Shelf, on page 111
DLP-L49 Connecting Office Power (AC) to the
NCS 2002 Shelf, on page 80
Required
Onsite
None
This task measures the power to verify correct power
and returns for the NCS 2002 shelf.