Mounting the Brackets on NCS 2006 Shelf
Tools/Equipment
Prerequisite Procedures
Required/As Needed
Onsite/Remote
Security Level
Procedure
Complete the necessary task as applicable:
•
DLP-L5 Mounting the Brackets on the NCS 2006 Shelf for ETSI Rack Configuration, on page 176
•
DLP-L6 Mounting the Air Deflectors (Front-to-Front) on the NCS 2006 Shelf for ETSI Rack
Configuration, on page 177
•
DLP-L7 Mounting the Bracket with Air Deflectors (Front-to-Back) on the NCS 2006 Shelf for ETSI
Rack Configuration, on page 179
•
DLP-L8 Mounting the Bracket with Air Deflectors (Front-to-Top) on the NCS 2006 Shelf for ETSI
Rack Configuration, on page 182
Stop. You have completed this procedure.
NTP-L46 Mounting the Brackets in ETSI Configuration
• #2 Phillips Dynamometric screwdriver
• Medium slot-head screwdriver
• Small slot-head screwdriver
• ETSI only:
◦ Six M6 x 20 pan-head Phillips mounting
screws
• ANSI only:
◦ Six #12-24 x 3/4 pan-head Phillips
mounting screws
DLP-L62 Unpacking and Verifying the Shelf , on
page 20
DLP-L63 Inspecting the Shelf, on page 22