Connecting Power and Ground
• Seventh, route the P3A cable under the P2A cable.
• Eighth, route the P4A cable under the P3A cable.
To install the DC distribution using the figure below :
Figure 194: Power Distribution Label - New Version
• First, route the P1A cable to the left of the chassis against the top of the power tray.
• Second, route the P2A cable under the P1A cable.
• Third, route the P3A cable under the P2A cable.
• Fourth, route the P4A cable under the P3A cable.
• Fifth, route the P1B cable to the right of the chassis against the top of the power tray.
• Sixth, route the P2B cable under the P1B cable.
• Seventh, route the P3B cable under the P2B cable.
• Eighth, route the P4B cable under the P3B cable.
This arrangement allows the management of cables within the boundaries of the chassis.
Note
Note
When transitioning to the rack, ensure that you maintain a two inch bend radius.

NTP-L57 Installing Power and Ground to the NCS 2015 Shelf

Purpose
NTP-L57 Installing Power and Ground to the NCS 2015 Shelf
This procedure installs power feeds and grounds the
NCS 2015 system.
Cisco NCS 2000 Series Hardware Installation Guide