Cisco Ncs 2000 Series Hardware Installation Guide - Cisco NCS 2006 Hardware Installation Manual

Ncs 2000 series
Table of Contents

Advertisement

Installing the Air Flow Regulator
Tools/Equipment
Required/As Needed
Onsite/Remote
Security Level
Before performing any of the following procedures, ensure that power is removed from the DC
Warning
circuit. Statement 1074
Before working on a chassis or working near power supplies, unplug the power cord on AC units.
Warning
Statement 246
This equipment is intended to be grounded. Ensure that the host is connected to earth ground during
Warning
normal use. Statement 39
For nominal voltage of -60 VDC, the input voltage range is from -40 to -72 VDC.
Note
Use only the fastening hardware provided with the NCS 2002 to prevent loosening, deterioration, and
Note
electromechanical corrosion of the hardware and joined material.
NTP-L42 Install the Air Plenum in NCS 2002 Shelf
• #2 Phillips Dynamometric screwdriver
• Medium slot-head screwdriver
• Small slot-head screwdriver
• Screws
◦ ANSI: #12-24 x 0.50 pan-head Phillips
screws
◦ ETSI: M6.0 x 20 pan-head Phillips screws
• Wing head screws (4)
• Adapter plates
• One air plenum kit (horizontal and vertical air
plenums)
As needed
Onsite
None

Cisco NCS 2000 Series Hardware Installation Guide

29

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Ncs 2002Ncs 201

Table of Contents