Commissioning
5.3 Commissioning with factory settings
5.3.2
Wiring examples for the factory settings
To ensure that the factory setting can be used, you must wire the terminal strip of your
inverter as shown in the following examples.
Factorry pre-assignment of the terminal block at the inverter with RS485 field bus interface
Figure 5-2
Note
Assignment of terminals following basic commissioning
The assignment of the terminal strip does not change once you have performed the basic
commissioning procedure.
54
Default wiring using RS485 communications
Operating Instructions, 01/2011, FW 4.4, A5E02999804A AB
SINAMICS G120C Inverter