Commissioning
5.5 Commissioning with STARTER
•
•
•
•
• Relinquish the master control after the motor
66
①
Open by double-clicking on the control panel
in STARTER.
②
Fetch the master control for the converter
③
Set the "Enable signals"
④
Switch on the motor.
The converter now starts to identify the motor
data. This measurement can take several
minutes. After the measurement the converter
switches off the motor.
data identification.
Operating Instructions, 01/2011, FW 4.4, A5E02999804A AB
SINAMICS G120C Inverter