Testing the sysload

Figure 107
Blower unit removal
Use Procedure 54 to test the sysload (manual reload) function.
Procedure 54
Sysload test
1
Start the sysload:
Simultaneously press the MAN RST buttons (the bottom buttons) on
both Call Processor Cards.
The following functions occur during a sysload:
The red LED at the top of the CPU column should light.
The major alarm indication should be displayed on all attendant
consoles.