Preparing to power up – AC

Connecting the AC power source

NN43021-310
Standard 06.01
Powering up the system and initial loading
Follow Procedure 41 to prepare to power up a Large System.
CAUTION
Verify that the safety grounds are properly connected.
Procedure 41
Preparing to power up – AC
1
Set the AC service panel circuit breakers OFF.
2
Set the main circuit breakers in the rear of each pedestal OFF.
3
Set the power supply or MPDU switches in each module OFF.
4
Set the ringing generators in each IPE or PE module OFF.
5
Set the blower unit switch in the front of each pedestal OFF.
6
Set all faceplate switches to ENB.
To connect a Large System to the AC power source, follow one of the two
options below.
Procedure 42
Option 1: Using the installed power plug (recommended)
Each column can be directly connected to the AC power source.
1
Connect the power plug from each column to the AC power respectable.
2
Proceed to "Turning AC power ON" on