STANDARD SYSTEM INSTALLATION
60
Eaton BladeUPS (12 kVA) User's Guide
2.
Pre-assemble four M6 hex nuts to the rail assembly:
Assemble two of the nuts and the rear hold-down bracket and finger-tighten
only. Assemble the other two nuts to the rail and finger-tighten only. See
Figure 44.
Repeat for the other rail.
Rear
Rear Hold-Down
Bracket
Figure 44. Installing the Rail Hardware (Right Rail Assembly Shown)
NOTE Verify that the holes in the rail align properly with the hole pattern in the rack. If the rack has square
holes, verify that the studs on the end of the rail align within the square holes.
3.
Using two M5 machine screws, attach the rail to the front of the rack and
finger-tighten only (see Figure 43 and Figure 45).
4.
Adjust the rail size on the rail assembly for the depth of your rack.
S
164201649 Rev 6 www.eaton.com/powerqualtiy
M6 Hex
Nuts
Rail Stud
(2 places)
Front M5 Screws
Figure 45. Securing the Front Rail