Rack Setup for the EBM

The EBM is heavy (see page 130). Removing the EBM from its carton requires a minimum of two people. Use
the corrugated lifting sling (packaged with the UPS) to move the UPS.
NOTE Mounting rails are required for each individual cabinet.
To install the EBM rail kit:
1.
Loosen the assembly wing nuts on both rail assemblies and adjust the rail size
for the depth of your rack (see Figure 35).
Front
Rail Assembly
2.
Select the proper holes in the rail for positioning the EBM and other cabinets in
the rack.
Place the first rail for the first EBM at the bottom, using positions 1 and 6 for the
front hex-head screws. If you are installing additional rails, place the next rail 4
holes above the last installed screw (see Figure 36).
NOTE Verify that the hole patterns on the rails and mounting brackets align with the hole pattern on the
rack.
Eaton BladeUPS (12 kVA) User's Guide
STANDARD SYSTEM INSTALLATION
C A U T I O N
Assembly Wing Nuts
Figure 35. Adjusting the Rail Depth