Commissioning (software)
6.5 Additional information on configuring the SINAMICS Integrated
Note
Vector drives in chassis format can also be operated with a current controller sampling time
of 400 µs (amongst other settings).
In the SIMOTION context, the following should be considered:
● A current controller sampling time of 400 µs is only possible if control is via a
● If the bus is operated isochronously, only cycle clocks with an integer multiple of 125 µs
● The PROFIBUS Integrated of a D4x5-2/CX32-2 is always isochronous! This means that a
● With CU parameter p0092 = 1, the sampling times are pre-assigned so that isochronous
Scenario 2: Current and speed controller cycle is not known
This procedure is especially suitable for devices in chassis format, as the current and speed
controller cycle also depends on the relevant device type.
1. To determine which cycle clocks are set in the SINAMICS drive unit after a project has
2. Use the "Download project to target system" menu command to download the
3. After the download has successfully completed, you will be able to determine all the
4. If required, it is now possible to optimize the T
Table 6- 5
Setting
T
DP
T
= T
I
T
MAPC
212
SINAMICS S120 control unit, which is not operated isochronously via
PROFIBUS/PROFINET on SIMOTION D.
are possible (i.e. 375 µs or 500 µs instead of 400 µs, for example).
current controller sampling time of 400 µs is not possible.
operation with a controller is possible.
been downloaded, first set reliable values for the cycle clocks in HW Config (see table
"Recommended cycle clock settings in HW Config").
parameterization.
current and speed controller clock cycles of the drives from the drives' expert lists.
p0115[0] current controller cycle clock
p0115[1] speed controller cycle clock
(see procedure for Scenario 1).
Recommended cycle clock settings in HW Config
= 3.0 ms
= 1.5 ms
O
= 3.0 ms
, T
, T
, and T
MAPC
DP
I
Explanation
T
= DP cycle time
DP
T
= time of actual value acquisition
I
T
= time of setpoint transfer
O
T
= master application cycle time
MAPC
Commissioning and Hardware Installation Manual, 02/2012