Grounding (NEBS-2000)

....................................................................................................................................................................................................................................
Procedure
....................................................................................................................................................................................................................................
3 - 2 4
Important! The following procedure describes the grounding of an
NEBS-2000 rack only! The ETSI-2 rack has to be grounded via the
PDP (see section "PDP Block-Diagram" (4-3)). The cables which are
mentioned below are not delivered as standard with the system but are
optional, i.e. they can be delivered as office-engineerable kits if a
dedicated grounding is needed.
............................................................................................................................................................
Connect the Office Grounding Cable — 848834974 (item 1) to the
1
top of the rack-frame using two hexagonal M8 bolts and hex. nuts M8
as shown in the figure below.
............................................................................................................................................................
Connect each separate shelf-grounding cable (item 2) to the top of
2
the rack frame with a hexagonal M5x16 bolt, Washer M5, tooth lock
— 901361949 and hex. nut M5as shown in the figure below for
Lower/Upper Subrack and Power Distribution Panel.
Ground Wire (800 mm [2,625 ft]) — CC848828158
Ground Wire (2000 mm [6,562 ft]) — CC848828174
Ground Wire (3000 mm [9,843 ft]) — CC848828182
E
S
N D
O F
T E P S
............................................................................................................................................................
Lucent Technologies
Equipment Installation
365-374-059
Issue a, January 2002