CHAPTER 6
Preparation Overview
Site Preparation Checklist for EX2300 Switches
Table 29: Site Preparation Checklist
Item or Task
Environment
Verify that environmental factors such as
temperature and humidity do not exceed switch
tolerances.
Power
Measure the distance between external power
sources and the switch installation site.
Locate sites for connection of system
grounding.
Calculate the power consumption and
requirements.
Copyright © 2017, Juniper Networks, Inc.
Site Preparation Checklist for EX2300 Switches on page 51
Environmental Requirements and Specifications for EX Series Switches on page 53
General Site Guidelines on page 57
Site Electrical Wiring Guidelines on page 57
Chassis Physical Specifications for EX2300 Switches on page 58
Rack Requirements on page 59
Requirements for Mounting an EX2300 Switch On or Under a Desk or Other Level
Surface or On a Wall on page 60
Cabinet Requirements on page 60
Clearance Requirements for Airflow and Hardware Maintenance for EX2300
Switches on page 61
The checklist in
Table 29 on page 51
preparing a site for EX2300 switch installation.
For More Information
"Environmental Requirements and
Specifications for EX Series Switches"
on page 53
"Power Specifications for EX2300
Switches" on page 67
summarizes the tasks you need to perform when
Performed by
Date
51