For lift control manifold service procedures, see Control
Manifold Cartridge Valve Service in this section. Refer
to Figure 71 for cartridge valve installation torque. Refer
to Figures 71 and 72 for hydraulic fitting installation
torque values.
NOTE: Solenoid valves SV1 and SV2 on the lift control
manifold use a coil spacer between the solenoid coil and
nut.
NOTE: Adjustment of Relief Valve (R7) is NOT recom-
mended.
IMPORTANT: A flow control orifice is placed be-
neath several of the hydraulic fittings on the lift con-
trol manifold (Fig. 72). The lift manifold uses three
(3) different orifice sizes. If a fitting is removed from
the lift control manifold and an orifice is in the man-
ifold port, make sure to remove orifice and label its
position for assembly purposes.
IMPORTANT: When installing orifice in manifold
(Fig. 72), make sure that orifice is flat in the base of
the fitting cavity. Manifold damage is possible if the
orifice is cocked in the cavity.
Reelmaster 5010- H
10 ft- lb
(14 N- m)
3
2
1
3
2
1
1. Fitting (2 used)
2. O- ring
3. Orifice (0.046)
Page 4 - 85
(14 N- m)
4
6
2
10 ft- lb
(14 N- m)
Figure 72
4. Orifice (0.028)
5. Fitting (6 used)
6. Orifice (0.055)