UPS Installation Plan and Unpacking
A supplemental 48 Vdc shunt trip signal for the battery disconnect device is provided, but is not required for
l
normal operation.
Battery Detect and 48 Vdc shunt trip wiring should be a minimum of 18 AWG
l
The REPO feature opens all switchgear in the UPS cabinet and isolates power from your critical load. Local
l
electrical codes may also require tripping upstream protective devices to the UPS.
The REPO switch must be a latching-type switch not tied to any other circuits.
l
A jumper wire must be connected between pins 3 and 4 on the REPO terminal block if using a
l
normally-closed REPO switch.
REPO wiring should be a minimum of 22 AWG and a maximum of 14 AWG.
l
The REPO switch wiring must be in accordance with NEC Article 725 Class 2 requirements.
l
The maximum distance between the REPO and the UPS cannot exceed 150 meters (500 feet).
l
3.3

Inspecting and Unpacking the UPS Cabinets

The cabinet is shipped bolted to a metal and wood pallet (see Figure 3-8 or Figure 3-9) with outer protective
packaging material covering the cabinet.
NOTE
The UPS cabinet is heavy (see Table 3-1). If unpacking and unloading instructions are not closely
followed, the cabinet may tip and cause serious injury.
1.
Carefully inspect the outer packaging for evidence of damage during transit.
Do not install a damaged cabinet. Report any damage to the carrier and contact an Eaton service
representative immediately.
NOTE
2.
Use a forklift or pallet jack to move the packaged cabinet to the installation site, or as close as possible,
before unpacking. If possible, move the cabinet using the pallet. Insert the forklift or pallet jack forks
between the supports on the bottom of the pallet (see Figure 3-5 or Figure 3-6 for the UPS cabinet center
of gravity measurements).
Do not tilt the UPS cabinet more than 10° from vertical or the cabinet may tip over.
3.
Set the pallet on a firm, level surface, allowing a minimum clearance of 3m (10 ft) on each side for
removing the cabinet from the pallet.
3-16
Eaton 93PM UPS (60–100 kW, 480V) Installation and Operation Manual P-164000227—Rev 2
Startup and operational checks must be performed by an authorized Eaton
Customer Service Engineer, or the warranty terms specified on page W-1 become
void. This service is offered as part of the sales contract for the UPS. Contact an
Eaton service representative in advance (a minimum two-week notice is required) to
reserve a preferred startup date.
For the following step, verify that the forklift or pallet jack is rated to handle the
weight of the cabinet (see Table 3-1 for cabinet weight).
WARNING
CAUTION
CAUTION
www.eaton.com/powerquality

Advertisement

Table of Contents
loading

Table of Contents