Ups Installation Plan And Unpacking; Creating An Installation Plan; Preparing The Site; Environmental And Installation Considerations - Eaton 93PM Installation And Operation Manual

Eaton 93pm ups 60–100 kw (480v)
Table of Contents

Advertisement

Chapter 3

UPS Installation Plan and Unpacking

Use the following basic sequence of steps to install the UPS:
1.
Create an installation plan for the UPS system (Chapter 3).
2.
Prepare your site for the UPS system (Chapter 3).
3.
Inspect and unpack the UPS cabinet (Chapter 3).
4.
Unload and install the UPS cabinet, and wire the system (Chapter 4).
5.
Install features, accessories, or options, as applicable (Chapter 4).
6.
Complete the Installation Checklist (Chapter 4).
7 .
Have authorized service personnel perform preliminary operational checks and start up the system.
3.1

Creating an Installation Plan

Before installing the UPS system, read and understand how this manual applies to the system being installed.
Use the procedures and illustrations in paragraph 3.2 and Chapter 4 to create a logical plan for installing the
system.
3.2

Preparing the Site

For the UPS system to operate at peak efficiency, the installation site should meet the environmental
parameters outlined in this manual. If the UPS is to be operated at an altitude higher than 1500m (5000 ft),
contact an Eaton service representative for important information about high altitude operation. The operating
environment must meet the weight, clearance, and environmental requirements specified.
3.2.1

Environmental and Installation Considerations

The UPS system installation must meet the following guidelines:
The system must be installed on a level floor suitable for computer or electronic equipment.
l
The system must be installed in a temperature and humidity controlled indoor area free of conductive
l
contaminants.
Failure to follow guidelines may void your warranty.
The UPS equipment operating environment must meet the weight requirements shown in Table 3-1 and the
size requirements shown in Figure 3-1 through Figure 3-7. Dimensions are in millimeters (inches).
NOTE
Startup and operational checks must be performed by an authorized Eaton
Customer Service Engineer, or the warranty terms specified on page W-1 become
void. This service is offered as part of the sales contract for the UPS. Contact an
Eaton service representative in advance (a minimum two-week notice is required)
to reserve a preferred startup date.