6.3.9

Battery Test

NOTE 1
This UPS has a user initiated battery test intended to determine if the
batteries are able to support the load.
NOTE 2
The battery test is only able to be initiated when the battery is fully
charged. This normally occurs within 72 hours of the start of a charging
cycle. The command will not be shown if the test is not able to be run.
To start the battery test:
1.
Tap the CONTROLS tab on the main menu navigation bar. The System Control screen is displayed.
2.
Tap the RUN BATTERY TEST button.

6.3.10 Using the UPS SHUTDOWN Command

A UPS shutdown is initiated by the Shutdown command on the UPS Control screen. The UPS SHUTDOWN
controls the UPS output by powering down the UPS and de-energizing the critical load.
The UPS (including Bypass) remains off until restarted.
To use the SHUTDOWN command:
1.
Tap the CONTROLS tab on the main menu navigation bar. The System Control screen is displayed.
All power to the critical load is lost when SHUTDOWN is selected in the following step. You should
use this feature only when you want to de-energize the critical load.
2.
Tap the SHUTDOWN button.
An action confirmation screen is displayed. Follow the on screen prompts to shut down the UPS or to
cancel or abort the shutdown. Selecting Shutdown will immediately shut down the UPS and de-energize
the critical load. Selecting Cancel will abort the shutdown
Do not attempt to restart the system after Load Off until the cause of the shutdown has been
identified and cleared.
3.
To restart the UPS after using the SHUTDOWN , follow the procedure in paragraph 6.3.1 or 6.3.2.
Power is present inside the UPS cabinet after the upstream input feeder circuit breakers are
opened because of the installed internal batteries.
Eaton 93PM UPS (60–100 kW, 480V) Installation and Operation Manual P-164000227—Rev 2
CAUTION
CAUTION
WARNING
www.eaton.com/powerquality
UPS Operating Instructions
6-13

Advertisement

Table of Contents
loading

Table of Contents