CAUTION:
Wear a grounded ESD strap when handling DC SAN Director components. The Director chassis
provides a grounding connection above the power connectors. Also, store ESD-sensitive components
in antistatic packaging.
1.
Before removing a blower assembly, verify that the other blower assemblies are functioning
correctly. The power LEDs should be steady green.
2.
Use the screwdriver to loosen the captive screws at the top and bottom of blower assembly.
3.
Support the blower assembly from underneath. Use the handle to remove the blower assembly
(see
Figure
Installing a blower assembly
To install a blower assembly
1.
Orient the blower assembly and slide it into the chassis, pushing firmly to ensure that it is seated.
2.
Verify that the power LED displays a green light.
90
Replacing DC SAN Director field-replaceable units (FRUs)
33).