B1 Overview of the operating sequence

General

The following operating sequence for
moving the balanced cantilever equip-
ment describes the standard
application.
Deviations are possible due to proj-
ect-specific requirements.
Detailed information regarding each
step is described in the following
sections.
The balanced cantilever equipment may
only be moved if the brakes are
applied.
32

Standard cycle sequence

The following working operations are
described in the respective sections.
Preparation – B2, B3
Release the formwork from the previ-
ous concreting section.
Lower the top and bottom slab
formwork.
Pushing the rail forward – C2
Release anchoring for the rail.
Raise the rail and gradually push for-
ward with the drive cylinder.
Anchor the rail.
Activating carriages – B4, B5
Activate front carriage.
Activate rear carriage.
Moving the balanced cantilever
equipment forward – C1
Gradually move the balanced cantilever
equipment forward with the drive
cylinder.
Deactivating carriage – B4, B5
Deactivate rear carriage.
Deactivate front carriage.
Subsequent work – B2,B3
Raise the top and bottom slab form-
work and anchor.
Set up the vertical formwork.
Install reinforcement.
Concreting
Concrete the next section.
VBC Balanced Cantilever Hydraulic System – Hydraulic System and Standard Cycle
Assembly Instructions

Advertisement

loading
Need help?

Need help?

Do you have a question about the VARIOKIT VBC and is the answer not in the manual?

Questions and answers

This manual is also suitable for:

Vbc 280