  • Page 1 CB 160 Climbing Formwork Instructions for Assembly and Use – Standard Confi guration Edition 04 l 2014...
  • Page 3: Table Of Contents

    General Load Models B4 Moving the units Standard work flow Preparation Moving procedure A1 Assembly of the CB 160 platforms Securing the unit Required resources Assembly of Console Bracket CB 160 C1 Planning and work preparation Assembly of girders Static system...
  • Page 4: Introduction

    10 VARIO GT 24 or TRIO formwork Bracket CB 160 with concreting scaffold 7 Wind bracing with tension belt 2 Adjusting Unit CB 160 or tie rod 11 Bracing with scaffold tubes 3 Adjustable Brace CB 164-224 8 Finishing Platform with Platform...
  • Page 5: Overview, Main Components

    CB 160 Climbing Formwork Introduction Overview, Main Components Anchoring to the building structure Variant 1 5.4 Threaded Anchor Plate DW 15* h ≥ 18.5 cm 5.5 Tie Rod DW 15*, Z-12.4-70 = h – 8 cm or Tie Rod B15*, Z-12.5-82 5.3 Climbing Cone 2 M24/DW 15...
  • Page 7: Standard Configuration

    CB 160 Climbing Formwork Introduction Standard Configuration General The working platform can be supple- The CB 160 climbing formwork is normally mented with: used as shoring in order to support an- – clamping unit, strongback and adjust- chored wall formwork in accordance able braces for accommodating the with EN 12812.
  • Page 8: Safety Instructions

    General The assemblies shown in these PERI Instructions for Assembly and Use are Additional PERI product information only examples which feature only one – Instructions for Use: Lifting Hook –...
  • Page 9: Load Models

    CB 160 Climbing Formwork Introduction Load Models Working position Concreting position The area-related live loads correspond The area-related live loads to EN 12811. correspond to EN 12811. Concreting Concreting platform platform 150 kg/m 150 kg/m Load Class 2 Load Class 2...
  • Page 10: Standard Work Flow

    CB 160 Climbing Formwork Introduction Standard work flow Preparation Initial use 1. Assemble wall formwork. 1. Position wall formwork for first wall 10. Place formwork on climbing plat- form and secure. 2. Assemble platforms. section. 11. Clean formwork and adjust if neces- 3.
  • Page 11 CB 160 Climbing Formwork Introduction Standard cycle 18. Attach finishing platform. 22. Mount wind bracing if required. 28. Remove advancing bolts and retract 19. Move Climbing Formwork to second formwork. 23. Clean formwork and adjust. 29. Mount scaffold mounting rings.
  • Page 12: A1 Assembly Of The Cb 160 Platforms

    CB 160 Climbing Formwork A1 Assembly of the CB 160 platforms Required resources 82 mm 82 mm Equipment and tools Hammer, wire pins, plumb line, approx. 0.50 m 4 screw clamps with 300 mm clamping 2 stop bars 1.0 m length, circular saw, electric drill, HSS drill Ø...
  • Page 13: Assembly Of Console Bracket Cb

    CB 160 Climbing Formwork A1 Assembly of the CB 160 platforms Assembly of Console Bracket CB 160 Assembly 1. Check centre-to-centre spacing if re- garding the planned measurement, or measure spacing of climbing cones already cast in concrete. 2. Adjust centre-to-centre spacing of brackets to the support (0.2).
  • Page 14: Assembly Of Girders

    CB 160 Climbing Formwork A1 Assembly of the CB 160 platforms 13.3 Assembly of girders When using PERI GT 24 girders, strengthen them on both sides in the area of the brackets with plywood strips (13.2). (Fig. A1.08) In order to avoid the risk of lifting in...
  • Page 15 CB 160 Climbing Formwork A1 Assembly of the CB 160 platforms Single girder position GT 24 Girder Timber – plywood or 3-ply board (13.2) – hex. wood screw 6 x 80 (13.3) – timber 8/16 (13.6) – GT 24 lattice girder (13.7) 13.6...
  • Page 16: Assembly Of Adjusting Unit Cb

    Adjusting Unit CB 160 SW 30 Assembly When using TRIO or VARIO GT 24, the Adjusting Unit CB 160 (2) has to be assembled with Hex. Bolts M20 x 150 (2.3), SW 30. Bolts M20 x 150 (2.3), SW 30. The Adjusting Bolt (2.2) points to the guardrail side.
  • Page 17: Assembly Of Decking

    Assembly of decking Climbing Platform, Working Platform Assembly 1. Cut planking at right angles. Length according to decking requirements. (Fig. A1.17 + A1.18) 13.5 2. At platform ends, fix each plank flush 13.1 to the girders (13.1 / 13.6). Planking is flush with bracket front edge on the wall side.
  • Page 18: Assembly Of Guardrails

    CB 160 Climbing Formwork A1 Assembly of the CB 160 Platforms 12.1 Assembly of guardrails Guardrail Post CB 1. Cut handrail boards (12.1) to match platform width. 12.5 2. Attach handrail boards to guardrail post with screw clamps. Height: 12.2 depends on decking design.
  • Page 19 CB 160 Climbing Formwork A1 Assembly of the CB 160 Platforms Assembly of guardrails 12.3 12.1 End Guardrail Post For longer cantilevers, it is necessary to additionally support the handrail boards with one or more end guardrail posts. 1. Mark the outside edge of the end guardrail post (12.3) on the handrail...
  • Page 20: A2 Other Assembly Work

    CB 160 Climbing Formwork A2 Other assembly work Assembly of 12.4 end guardrail posts Required materials: – 2 end guardrail posts – 2 handrail boards 4 x 12 cm – 1 toe board 4 x 12 cm Assembly 1. Fix end guardrail post (12.4) to girders with wood screws 6 x 80 (5x) (12.8).
  • Page 21: Assembly Of Hinged Hatch Cover

    CB 160 Climbing Formwork A2 Other assembly work Assembly of hinged hatch cover 14.9 Pre-assembly – For installation, a 72 x 57 cm cut-out is made in the planking between the brackets. 14.8 – Remaining planking width > 10 cm.
  • Page 22: Assembly Of Finishing Platform

    – If no girders have been included in the planning, they can be selected in Part C1 platform deckings. – When using PERI GT 24 girders, they are to be strengthened on both sides 13.5 at the level of the platform beams with 3S sheets, see A1.
  • Page 23: Finishing Tasks

    CB 160 Climbing Formwork A2 Other assembly work Assembly of finishing platform Assembly in the area of the 180 mm 100 mm platform girder – The planking is divided along the mid- dle of the platform girder (8.1). – The planking (8.3) to the side of the platform post (9.1) is complete!
  • Page 24: B1 Work On The Construction Site

    CB 160 Climbing Formwork B1 Work on the construction site Anchoring Safety instructions – Each CB bracket must be individu- ally anchored, and the loosening or dismantling of the anchoring may only take place on the side of the load transfer. The positioning of two cones against each other is not allowed.
  • Page 25 CB 160 Climbing Formwork B1 Work on the construction site Anchoring Preparations for use – With different concreting heights, an- chor spacings with < 5 cm deviations can be compensated by means of the height adjusting unit. With larger de- viations, more drilled holes are pro- vided.
  • Page 26 CB 160 Climbing Formwork B1 Work on the construction site Anchoring Assembly of the leading anchor 5.11 with Anchor Positioning Stud M24, 5.12 e.g. for TRIO panel formwork. Initial use and standard use 1. Fix Anchor Positioning Stud M24 (5.11) to the marked position with nails 31 x 80 (4x) (5.12).
  • Page 27 CB 160 Climbing Formwork B1 Work on the construction site Anchoring Assembly of the leading anchor with Advancing Bolt M24, e.g. for VARIO GT 24 girder wall formwork. Initial use 1. Check the required space for the An- chor Positioning Plate M24 (5.10).
  • Page 28 Striking 1. Loosen connections to the adjoining elements (VKZ couplings, BFD align- ment coupler). 2. Loosen Height Adjusting Unit CB 160 (2). 3. Tilt formwork using Adjustable Brace CB 164-225 (3.1). (Fig. B1.15) With this, the nails from the Anchor Positioning Stud M24 (5.12) and box...
  • Page 29 CB 160 Climbing Formwork B1 Work on the construction site Anchoring Check if the cone fits correctly and is clean. 5.11 Assembly of Scaffold Mounting Ring M24 1. Remove the Anchor Positioning Stud M24 (5.11) from the cone with an Allen Key SW 14.
  • Page 30: Mounting The Climbing Platform Cb

    CB 160 Climbing Formwork B1 Work on the construction site Mounting the climbing platform CB 160 to the first wall section – Use 4-sling lifting gear with suffi- ciently long chains and securing devices! – Crane sling angle max. 30°! –...
  • Page 31 CB 160 Climbing Formwork B1 Work on the construction site Mounting the CB 160 climbing platform to the first wall section Assembly 4. Lift platform and pivot over the scaffold mounting rings. (Fig. B1.21) 5. Bring platform into position and simultaneously lower without tilting.
  • Page 32: Mounting The Finishing Platform Cb

    CB 160 Climbing Formwork B1 Work on the construction site Mounting of the finishing platform CB 160 Preparation Connecting to the brackets 1. Remove tacked on planking parts Connections are done using Bolts from both sides of the platform M16 x 130 ISO 4014-8.8 and self-securing beam.
  • Page 33 CB 160 Climbing Formwork B1 Work on the construction site Mounting the finishing platform CB 160 Fixing points for the Platform Posts CB 225 and Guardrail Posts CB 190 and 370. Firstly, only loosely tighten the bolt Fig. B1.26a (9.6) for an articulated connection.
  • Page 34 CB 160 Climbing Formwork B1 Work on the construction site Fitting of the finishing Platform CB 160 Finishing tasks 12.1 Fig. B1.27 Fig. B1.28 Fig. B1.29 7. Slowly lift the platform unit. 9. Lower the platform unit from the 12. Mount wind bracing (7), see B1 As- The finishing platform (8) pivots under...
  • Page 35: Assembly Of Wind Bracing

    CB 160 Climbing Formwork B1 Work on the construction site Assembly of wind bracing With tension belt 25 kN Permissible tension anchor force = 25 kN. 1. Attach Belt Connector CB (7.2) with Bolt M16 x 100, SW 24, to the vertical tube of the bracket (1.2).
  • Page 36 CB 160 Climbing Formwork B1 Work on the construction site Assembly of wind bracing With Tie Rod DW 15 Permissible tension anchor force = 41 kN. 1. Fix Tension Anchor Connector CB (7.3) with designated Bolt M16 x 100, SW 24, to vertical tube of the bracket (1.2).
  • Page 37: Removal Of The Climbing Cones

    3. Unscrew cone by hand. (Fig. B1.35b) Fig. B1.35b For architectural concrete or gas/water impermeability of the wall, the cone hole can be closed with PERI Sealing Cones KK. See PERI Tie Technology or contact your PERI sales engineer. (Fig. B1.35c) Fig.
  • Page 38: Ladder Assembly

    CB 160 Climbing Formwork B1 Work on the construction site Ladder assembly Concreting height 1.50 – 3.10 m Concreting height 2.00 – 3.60 m Overview Mounting of ladder is dependent on the 15.6 position of the finishing platform. 15.6 There are four concreting heights.
  • Page 39 CB 160 Climbing Formwork B1 Work on the construction site Ladder assembly Pre-assembly of ladder 15.7 15.1 1. Use ladders: SW 19 Top: Ladder 220/6 (15.1) 15.3 15.5 Bottom: Ladder 180/6 (15.2) SW 19 2. Connect ladders with bolts SW 19 (15.3).
  • Page 40: B2 Assembly Of Formwork Elements

    CB 160 Climbing Formwork B2 Assembly of formwork elements VARIO GT 24 element Assembly of Strongback CB on the VARIO GT 24 element 1. Lay Strongback CB 270 or CB 380 (4) on the steel waler of the VARIO GT 24 formwork according to the bracket spacing.
  • Page 41 B2 Assembly of formwork elements VARIO GT 24 element SW 19 Assembly of VARIO GT 24 formwork element on CB 160 Bracket 5. Fix Adjustable Brace 164-224 (3.1) to 1. Completely move back the sliding the bracket using bolts and cotter block (2.1) of the Adjusting Unit...
  • Page 42 CB 160 Climbing Formwork B2 Assembly of formwork elements VARIO GT 24 element Moving of VARIO GT 24 elements Kranlasche 24 Art.-Nr. 070760 Originalbetriebsanleitung 10.6 10.5 Follow the instructions of use for the Crane Splice 24! Dismantling 10.2 1. Move back the sliding block (2.1) in the...
  • Page 43 CB 160 Climbing Formwork B2 Assembly of formwork elements VARIO GT 24 element Moving of VARIO GT 24 elements Preparation for initial assembly 1. Move back the sliding unit (2.1) in the adjusting unit, SW 19, see B3. 10.2 2. Fix Strongback CB (4) to the adjusting unit by means of bolts Ø...
  • Page 44: Trio Element

    CB 160 Climbing Formwork B2 Assembly of formwork elements TRIO eElement Connector TRIO-CB left cantilevering right cantilevering Mounting of Strongback CB on TRIO elements 1. Assemble TRIO elements on the assembly area to form formwork units. 2. Fix Connector TRIO-CB (4.5) to panel struts with bail pin Ø...
  • Page 45 CB 160 Climbing Formwork B2 Assembly of formwork elements TRIO element SW 19 Mounting of formwork element on CB 160 Bracket 5. Fix Adjustable Brace 164-224 (3.1) 1. Move back the sliding block (2.1) in the adjusting unit (2), SW 19, to bracket using bolts and cotter pins (Fig.
  • Page 46 CB 160 Climbing Formwork B2 Assembly of formwork elements TRIO element Exchange of formwork Versetzhaken MAXIMO 1,5 t Art.-Nr. 115168 10.5 Originalbetriebsanleitung 10.6 10.2 Follow Instructions for Use: Lifting Hook MAXIMO 1.5 t! Dismantling 1. Move back the sliding block (2.1) in...
  • Page 47 CB 160 Climbing Formwork B2 Assembly of formwork elements TRIO element Exchange of formwork elements 10.2 Preparation for initial assembly 10.6 1. Move back the sliding unit (2.1) in the 10.3 adjusting unit, SW 19, see B3. 2. Fix Connectors CB (4.5) to the Strongback CB (4) using bolts Ø...
  • Page 48: B3 Formwork Utilisation

    CB 160 Climbing Formwork B3 Formwork Utilisation Utilisation of adjusting unit CB 160 Adjusting Unit Adjusting Unit CB 160 (2) SW 19 Sliding block with hole Ø 26 (2.1) Adjusting bolt SW 19 (2.2) Hex. bolt ISO 4014 (2.3) M20 x 150-8.8 and nut ISO 7042 (2x) Ratchet Lever SW 19 (2.5)
  • Page 49: Formwork Alignment

    CB 160 Climbing Formwork B3 Formwork Utilisation Formwork alignment Height adjustment with the Connector TRIO-CB 1. On the top Connector, alter the adjusting spindle (4.8) for necessary clearance. 2. On the lower Connector, lower ad- justing spindle (4.8) onto the locking pin (4.6).
  • Page 50: Inclination Adjustment

    CB 160 Climbing Formwork B3 Formwork Utilisation Formwork alignment Inclination adjustment with the Adjustable Brace CB 164-224 The required inclination of the form- work is achieved by altering the Adjust- able Brace CB 164-225 (3.1). Depending on the rotational direction, the formwork moves forward or re- tracts.
  • Page 51: B4 Moving The Units

    CB 160 Climbing Formwork B4 Moving the units Preparation Do not exceed the crane capacity! 10.3 1. Loosen tie point and remove tie rod. 2. Move formwork away from the wall by means of the Adjusting Unit (2), see B3. Tilt formwork in the direction of the guardrails using the Adjustable Brace (3.1).
  • Page 52: Moving Procedure

    CB 160 Climbing Formwork B4 Moving the units Moving procedure 5.6b Use a guide rope to ensure con- trolled movements of the platform when being moved. Any open edges created during the climbing procedure are to be made safe or cordoned off.
  • Page 53: Securing The Unit

    CB 160 Climbing Formwork B4 Moving the units Securing the unit If the securing bolts cannot be 10.3 inserted, repeat the procedure! 1. Enter platform. 2. Insert safety pins (1.5) under the Scaffold Mounting Ring (5.6). (Fig. B4.03 + B4.03a) Use cut-out in the planking.
  • Page 54: C1 Planning And Work Preparation

    CB 160 Climbing Formwork C1 Planning and work preparation for the platforms Static system and load combinations The charts serve the detailed determi- Load Combination A – Working nation of the bearing forces with regard Wind load: to the load combinations. For all load q = 0.25 kN/m...
  • Page 55: Platform Dimensioning

    CB 160 Climbing Formwork C1 Planning and work preparation Platform dimensioning Special applications Standard applications Differing loads, larger formwork heights When planning the platforms, existing or inclinations of the building require a widths of influence of the brackets are to be determined.
  • Page 56 CB 160 Climbing Formwork C1 Planning and work preparation Platform decking – The execution of the platform decking must be carried out according to DIN EN 12811. – All materials used must be of sufficient quality, see Table 6. – Tripping hazards, unnecessary box outs and openings in the decking are to be avoided or covered.
  • Page 57 2.40 5.53 Timber 16 x 16 The illustration and table conform to Appendices K12 and K13 of Type Test CB 160 carried out by the State Structural Inspectorate in Düsseldorf (Inspection Certificate No. IIB 4-540-136/91) and may only be used in accordance with the provisions of this type test.
  • Page 58: Platform Decking

    CB 160 Climbing Formwork C1 Planning and work preparation Platform decking Layout of main platform – 80 60 80 60 when used as formwork scaffold Fig. C1.03a Layout of main platform – when used as working scaffold (Platform above the bracket) Fig.
  • Page 59: Handrails And Guardrails

    CB 160 Climbing Formwork C1 Planning and work preparation Handrails and guardrails On all platform levels, edges are to be protected with guardrails. In order to maintain permissible spans and cantile- vers, additional guardrail posts can also be mounted, see Table 4.
  • Page 60: Connecting Vario Gt 24 Formwork

    CB 240 Climbing Formwork C1 Planning and work preparation Connecting VARIO GT 24 formwork Mounting the leading anchor During formwork design, attention must be paid that there is sufficient spacing between the bracket axis and the GT 24 formwork girder. Otherwise, mounting the Leading An- chor (5) with the Anchor Positioning Stud M24 (5.9) is not possible.
  • Page 61 CB 240 Climbing Formwork C1 Planning and work preparation Connecting VARIO GT 24 formwork Adjustable Brace 164-224 According to the formwork waler spac- ing, fix the adjustable brace (3.1) with bolt Ø 25 x 180 (3.2) in the bottom hole (Fig.
  • Page 62: Connecting Trio Formwork

    CB 160 Climbing Formwork C1 Planning and work preparation Connecting TRIO formwork Connection to horizontal struts Connection to vertical struts Height of girder: 24 cm Height of girder: 24 cm With a plywood projecting end of 5 cm and an adjusting length of approx.
  • Page 63 CB 160 Climbing Formwork C1 Planning and work preparation Connecting TRIO formwork TR 270 x 240 element in an upright position The Connector TRIO-CB is to be bolted to the vertical struts. (Fig. C1.12.1 – C1.12.3) The illustrations show girders with a height of 24 cm.
  • Page 64: Moving The Units

    CB 160 Climbing Formwork C1 Planning and work preparation Moving the units Installation of compression brace ≤ 45° In order to prevent the strongbacks from being pulled out of line during the lifting process due to the redirection of forces, clamp a suitable piece of timber (4.10) as a compression brace between...
  • Page 65: Ladder Access

    CB 160 Climbing Formwork C1 Planning and work preparation Ladder Access Table 6 Parts list for ladder access Concreting height [m] 1.5 – 3.0 2.0 – 3.0 3.3 – 4.9 3.8 – 5.4 3.65 4.15 5.45 5.95 Working platform - finishing platform spacing [m] Item no.
  • Page 66: Use On Circular Structures

    CB 160 Climbing Formwork C1 Planning and work preparation Use on circular structures Parallel arrangement of brackets < 10° Depending on bracket spacing c, brackets can be positioned parallel to each other as of a certain radius of the building.
  • Page 67: Corner Platforms

    CB 160 Climbing Formwork C1 Planning and work preparation Corner platforms Corner platforms are to be erected in such a way that free access is possible around the corners of the building when the formwork has either been shuttered or retracted.
  • Page 68: Use As Working And Safety Scaffold

    Handrail Post 200. If necessary, the position of the timber 16/16 and the Platform Fig. C1.21 Connection CB 160 is to be changed. (Fig. C1.21) Instructions for Assembly and Use – Standard Configuration...
  • Page 69 CB 160 Climbing Formwork Protective access scaffold according to DIN 4420 Open slab edges are to be secured at 1,0 m the scaffold ends with guardrails! For decking consisting of planks, the permissible falling height h is depend- ent on the dimensions of the planks which have been used Table 7).
  • Page 70: Components

    Complete with Complete Climbing Scaffold Bracket CB 160. 2 pc. 017040 Screw-On Coupler AK 48, galv. 1 pc. 701209 Guardrail Post CB 160 1 pc. 710222 Bolt ISO 4014 M16 x 80-8.8, galv. 1 pc. 070890 Nut ISO 7042 M16-8, galv.
  • Page 71 Complete with For mounting platform decking on the Climbing 2 pc. 711078 Bolt ISO 4014 M20 x 130-8.8, galv. Bracket CB 160 when used as working scaffold. 2 pc. 781053 Nut ISO 7042 M20-8, galv. Note Follow Instructions for Use! Technical Data Permissible load-bearing capacity 500 kg.
  • Page 72 CB 160 Climbing Formwork Item no. Weight kg 051110 24,900 Adjustable Brace CB 164-224 Complete with For aligning the Strongback CB. 2 pc. 715936 Pin Ø 25 x 180, incl. dowel pin Ø 6 2 pc. 018060 Cotter Pin 4/1, galv.
  • Page 73 CB 160 Climbing Formwork Item no. Weight kg 051230 17,000 Finishing Platform Beam CB Complete with For assembling finishing platforms. 4 pc. 710232 Bolt ISO 4014 M16 x 130-8.8, galv. 4 pc. 070890 Nut ISO 7042 M16-8, galv. M 16x130 Ø17...
  • Page 74 CB 160 Climbing Formwork Item no. Weight kg 051050 26,400 Post Extension CB 180 Complete with For assembling finishing platforms. In combination 2 pc. 710232 Bolt ISO 4014 M16 x 130-8.8, galv. with Platform Post CB 225 for concreting heights 2 pc.
  • Page 75 CB 160 Climbing Formwork Item no. Weight kg Handrail Posts CB Complete with 051210 19,000 Handrail Post CB 190 2 pc. 710232 Bolt ISO 4014 M16 x 130-8.8, galv. 051220 34,600 Handrail Post CB 370 2 pc. 070890 Nut ISO 7042 M16-8, galv.
  • Page 76 CB 160 Climbing Formwork Item no. Weight kg 017040 0,850 Screw-On Coupler AK 48, galv. For Scaffold Tubes Ø 48 mm. SW 30 SW 19 051160 0,894 Guardrail Connector CB For assembling scaffold tubes on handrail posts. Ø48 SW 19 Accessories F.H.
  • Page 77 For the extention of guardrail post CB by 50 cm. 1 pc. 710222 Bolt ISO 4014 M16 x 80-8.8, galv. 1 pc. 070890 Nut ISO 7042 M16-8, galv. Ø17 Ø10 065066 15,100 End Guardrail Frame 55 Clampable end guardrail for all PERI scaffold platforms and climbing systems.
  • Page 78 CB 160 Climbing Formwork Item no. Weight kg 051640 0,014 Lag Screw DIN 571 6 x 80, galv. SW 10 051650 0,060 F.H. Bolt DIN 603 M6 x 180 MU, galv. With nut. SW 10 F. H. Bolts DIN 603 M8...
  • Page 79 CB 160 Climbing Formwork Item no. Weight kg 114158 1,030 Screw-On Cone-2 M24/DW 20, galv. Note Anchor system M24. Separate design information on request. For anchoring climbing systems. SW 36 Accessories Threaded Anchor Plate DW 20 030860 0,801 030860 0,801...
  • Page 80 CB 160 Climbing Formwork Item no. Weight kg Tie Rods DW 15 Note 030030 1,440 Tie Rod DW 15, Spec. Length Non-weldable! Take official approval into 030050 0,000 Cutting Cost Tie Rod DW 15, B 15 consideration! Technical Data Permissible tension force 90 kN.
  • Page 81 CB 160 Climbing Formwork Item no. Weight kg 029270 0,331 Advancing Bolt M24, galv. For fixing the M24 anchor system if the plywood formlining is drilled through. M 24 SW 19 Accessories Anchor Positioning Plate M24, galv. 029280 0,196 029280 0,196 Anchor Positioning Plate M24, galv.
  • Page 82 CB 160 Climbing Formwork Item no. Weight kg 107007 3,410 Tension Anchor Connector CB Complete with To prevent tipping over due to wind loads with Tie 1 pc. 710219 Bolt ISO 4014 M16 x 100-8.8, galv. Rod DW 15. 1 pc. 070890 Nut ISO 7042 M16-8, galv.
  • Page 83 CB 160 Climbing Formwork Item no. Weight kg 051260 3,300 Tension Belt Connector CB Complete with To prevent tipping over due to wind loads with 1 pc. 710219 Bolt ISO 4014 M16 x 100-8.8, galv. tension belt. 1 pc. 070890 Nut ISO 7042 M16-8, galv.
  • Page 84 CB 160 Climbing Formwork Item no. Weight kg 116752 5,050 Wall Bracing Shoe CB M24 Complete with To prevent tipping over due to wind loads with 2 pc. 104031 Fitting Pin Ø 21 x 120 Tension Belt or Tie Rod DW 15 and to stabilise the 2 pc.
  • Page 85 CB 160 Climbing Formwork Item no. Weight kg 027212 0,445 Allen Key SW 14, long Fits to PERI Anchor Positioning Studs and Allen Key Bolts M16. SW 14 072180 0,560 Ratchet Wrench 1/2" 029620 0,075 Socket SW 19-1/2" Fits to Hex. Bolts M12 or Height Adjusting Unit SW 19.
  • Page 86 Ladder Access for Climbing Systems Item no. Weight kg 126431 12,300 Hatch 55 x 60-2, foldable Complete with Self-closing hatch for ladder access. Clear opening 1 pc. 126785 Hatch Hinge RCS approx. 55 x 60 cm. Ladder fixation with bolts or 12 pc.
  • Page 87 Item no. Weight kg 051410 11,700 Ladder 180/6, galv. Complete with As access for PERI formwork systems. 4 pc. 710224 Bolt ISO 4017 M12 x 40-8.8, galv. 4 pc. 710381 Nut ISO 7042 M12-8, galv. 5 x 298 = 1490...
  • Page 88 4 pc. 710266 Bolt ISO 4017 M12 x 25-8.8, galv. 051450 25,200 Ladder Safety Cage 150, galv. 4 pc. 701763 Clamping Plate Fl 25 x 10 x 90 Ladder safety cage for PERI access ladders. SW 19 111165 6,080 Ladder Connector VARIO, adjustable...
  • Page 90 Belgium/Luxembourg Turkey Finland Brazil Greece N.V. PERI S.A. PERI Kalip ve Iskeleleri Sanayi PERI Suomi Ltd. Oy PERI Formas e PERI Hellas Solely Owned Ltd. 1840 Londerzeel ve Ticaret Ltd. 05460 Hyvinkää Escoramentos Ltda. 194 00 Koropi info@peri.be...
  • Page 91 Morocco Ukraine Croatia Algeria Colombia PERI S.A.U. PERI Ukraina PERI oplate i skele d.o.o. Sarl PERI PERI S.A.S. Colombia Tanger 07400 Brovary 10 250 Luöko-Zagreb Kouba 16092, Alger Briceño, Cundinamarca info@peri.ma peri@peri.ua info@peri.com.hr info@peri.com peri.colombia@peri.com.co www.peri.ua...
  • Page 92 Slab Formwork Climbing Systems Tunnel Formwork Bridge Formwork Shoring Systems Construction Scaffold Facade Scaffold Industrial Scaffold Access Protection Scaffold System-Independent Accessories Services PERI GmbH Formwork Scaffolding Engineering Rudolf-Diesel-Strasse 19 89264 Weissenhorn Germany Tel. +49 (0)7309.950-0 Fax +49 (0)7309.951-0 info@peri.com www.peri.com...