Commissioning The Primary Battery Cabinet - SMA COMMERCIAL STORAGE SOLUTION 30 System Manual

Table of Contents

Advertisement

SMA Solar Technology AG
Requirements:
☐ The inverter has been correctly mounted and connected.
☐ The inverter enclosure cover is securely closed.
☐ The battery has been correctly mounted and connected.
☐ All battery cabinets are securely closed.
☐ The supplied energy meter has been correctly mounted and connected (see manufacturer's manual).
☐ The DC distributor has been correctly mounted and connected (see manufacturer's manual).
Procedure:
1. If a SMA Data Manager is available, activate the SMA Data Manager (see manual for the SMA Data Manager).
2. On a secondary battery cabinet, press the external switch on the outside of the cabinet door.
3. On the battery management system of this secondary battery cabinet, press the SWITCH control element.
4. Activate the display on the battery management system. To do this, tap with the fingers on the highlighted area
beside the display.
☑ The battery management system display shows the number of battery modules detected.
5. If the number of battery modules detected does not match the
number of battery modules installed, disconnect the battery from
the voltage source and check all battery communication
connections.
6. If the number of battery modules detected is still incorrect after eliminating any battery communication faults,
contact Service.
7. If the number of battery modules detected matches the number of battery modules installed, confirm the correct
number of battery modules. To do this, tap with the fingers on the highlighted area beside the display.
8. Commission all other secondary battery cabinets in the same way.
Also see:
• Safety when Commissioning the Battery ⇒ page 92
• Checking the Mounting and Connection Work ⇒ page 89
• Design of the Battery Cabinet ⇒ page 36
• Connection Area of the Battery Management System ⇒ page 75
• Battery Event Messages ⇒ page 152
9.4.8

Commissioning the Primary Battery Cabinet

Performing system registration
To complete commissioning, a system registration must be performed
• Use the following link for the system registration: https://my.sma-service.com/.
Requirements:
☐ The inverter has been correctly mounted and connected.
☐ The inverter enclosure cover is securely closed.
☐ The battery has been correctly mounted and connected.
☐ All battery cabinets are securely closed.
☐ The supplied energy meter has been correctly mounted and connected (see manufacturer's manual).
System Manual
9 Commissioning
ESSX-20-SH-en-10
97