9 Commissioning
System with one primary battery cabinet and two secondary battery cabinets
Device
Primary battery cabinet
Secondary battery cabinet 1
Secondary battery cabinet 2
System with one primary battery cabinet and three secondary battery cabinets
Device
Primary battery cabinet
Secondary battery cabinet 1
Secondary battery cabinet 2
Secondary battery cabinet 3
Also see:
• Setting Option for Address and Terminator ⇒ page 93
• Setting the Address and Terminator ⇒ page 94
9.4.5
Setting the Address and Terminator
The address and terminator only need to be set on the battery management system in systems with more than one
battery cabinet. Always set the address and terminator as described in this section.
Performing system registration
To complete commissioning, a system registration must be performed
• Use the following link for the system registration: https://my.sma-service.com/.
94
ESSX-20-SH-en-10
Address
ADDRESS setting: 0/0
Left rotary switch to 0
Right rotary switch to 0
ADDRESS setting: 2/0
Left rotary switch to 2
Right rotary switch to 0
ADDRESS setting: 2/1
Left rotary switch to 2
Right rotary switch to 1
Address
ADDRESS setting: 0/0
Left rotary switch to 0
Right rotary switch to 0
ADDRESS setting: 2/0
Left rotary switch to 2
Right rotary switch to 0
ADDRESS setting: 2/1
Left rotary switch to 2
Right rotary switch to 1
ADDRESS setting: 2/2
Left rotary switch to 2
Right rotary switch to 2
SMA Solar Technology AG
Terminator
TERM switch to ON
TERM switch to OFF
TERM switch to ON
Terminator
TERM switch to ON
TERM switch to OFF
TERM switch to OFF
TERM switch to ON
System Manual