Checking The Mounting And Connection Work - SMA COMMERCIAL STORAGE SOLUTION 30 System Manual

Table of Contents

Advertisement

SMA Solar Technology AG
Procedure
10.
Perform the configuration with the help of the instal-
lation assistant. Make the following settings:
11.
Complete commissioning of the primary battery
cabinet.
Complete commissioning of the individual battery
cabinet.
12.
Configure the temperature and humidity sensor.
13.
Commission the energy meter.
14.
To monitor the PV system and visualize the PV sys-
tem data, register in the Sunny Portal and create
the system in Sunny Portal or add devices to an ex-
isting system.
9.2

Checking the Mounting and Connection Work

Before commissioning or during setup, perform a thorough check of all mounting and connection work. The basis for
the check is DIN VDE 0100-600.
Procedure:
1. Ensure that the inverter has been correctly mounted and connected.
2. Ensure that the battery has been correctly mounted and connected. In particular, ensure adherence to the
requirements for the installation site and the local fire protection regulations.
3. If there is more than one battery cabinet: Ensure that the supplied DC distributor has been correctly mounted and
connected.
4. If there is more than one battery cabinet: Ensure that the address and terminator has been correctly set on the
battery management system of each battery cabinet.
5. Ensure that the supplied energy meter has been correctly mounted and connected (see manual for the energy
meter).
6. Measure the ground resistance and continuity of the grounding conductor.
7. Measure the insulation resistance.
8. Check the polarity between the inverter and battery.
9. Ensure that the circuit breaker of the DC distributor is switched on.
System Manual
• Administrator registration
• Device configuration (device name, device
function)
• Adding devices (e.g., energy meter, PV
inverter)
• Country data set
• Energy meter at the point of interconnection
• Battery configuration
• Energy management
• Grid management services
9 Commissioning
See
Section 9.3.3, page 91
Section 9.4.8, page 97
Section 9.4.6, page 95
Section 9.5, page 99
See manual for the energy meter
https://www.sunnyportal.com
ESSX-20-SH-en-10
89