Commissioning The Battery; Commissioning Procedure - SMA ENERGY SYSTEM with SUNNY BOY STORAGE 3.8-US System Manual

Hide thumbs Also See for ENERGY SYSTEM with SUNNY BOY STORAGE 3.8-US:
Table of Contents

Advertisement

SMA Solar Technology AG
6
Commissioning
6.1

Commissioning Procedure

This section describes the commissioning procedure and gives an overview of the steps you must
always perform in the prescribed order.
Procedure
1.
Commission the battery.
2.
Commission and configure the battery inverter.
3.
Set the time-of-use (optional).
4.
Set the Peak Load Shaving function (optional).
5.
Register system in Sunny Portal.
6.2

Commissioning the Battery

• Switch on the battery.
6.3
Commissioning and Configuring the Battery Inverter
6.3.1
Commissioning the Battery Inverter
• Switch on the AC circuit breaker.
☑ All three LEDs light up. The start-up phase begins. All three LEDs go out again after
approximately 90 seconds.
☑ Depending on the available power, the green LED pulses or is continuously illuminated. The
inverter is feeding in.
6.3.2
Establishing a Connection to the User Interface of the
Battery Inverter
SSID, IP address and necessary passwords
• SSID in WLAN: SMA[serial number] (e.g. SMA0123456789)
• Standard WLAN password (usable until completion of the configuration by means of the
installation assistant or prior to the end of the first ten feed-in hours): SMA12345
• Device-specific WLAN password (usable after initial configuration and completion of the
first ten feed-in hours): see WPA2-PSK on the type label of the inverter or on the back of
the manual included in the delivery
• Standard IP address for a direct connection via WLAN outside of a local network:
192.168.12.3
System Manual
6 Commissioning
See
Section 6.2, page 19
Section 6.3, page 19
Section 6.3.4, page 21
Section 6.3.5, page 22
Section 6.4, page 23
SBSUL9540-SH-en-10
19

Advertisement

Table of Contents
loading

Table of Contents