UPS5000-S-1200 kVA
User Manual
Figure 3-41 Connecting the signal cables
----End
3.2.5 Installing Optional Components
3.2.5.1 Installing a Battery Grounding Failure Detector
Prerequisites
●
●
Procedure
Step 1 Remove the top cover from the power unit, and remove the bracket of the battery
grounding failure detector.
Issue 10 (2023-05-26)
If the power units share battery strings, you need to install a battery
grounding failure detector only in power unit 1.
If the power units do not share battery strings, you need to install battery
grounding failure detectors in both power units.
Copyright © Huawei Digital Power Technologies Co., Ltd.
3 Installation
85