Figure 3-72 Reinstalling the cover
Step 8 Switch on the circuit breaker.
Step 9 Clear the fault alarm.
----End

3.2.5.4 Connecting Cables Between the UPS and the SmartLi

Prerequisites
If the SmartLi is configured, perform the following steps to connect cables.
Procedure
Step 1 Connect cables between the UPS and the SmartLi.
1.
2.
● Connect the ground cable of the SmartLi or its BBB box to the battery PE of the
● Route a signal cable out of the cabinet only from the top of the bypass unit, as
● The number and colors of cables are for reference only.
Issue 10 (2023-05-26)
Connect battery cables of each power unit to the SmartLi or BBB box.
Connect the COM2 port on the monitoring interface card (MUS05A) in the
control module of each power unit to the COM port on the master SmartLi
cabinet of the corresponding power unit.
NO TICE
UPS or the ground bar in the equipment room based on the site survey.
shown in the figure.
Copyright © Huawei Digital Power Technologies Co., Ltd.