Installing Optional Components; Installing Antiseismic Kits - Huawei UPS5000-E-400K-SM User Manual

Hide thumbs Also See for UPS5000-E-400K-SM:
Table of Contents

Advertisement

UPS5000-E-(350 kVA-800 kVA)
User Manual (50 kVA Power Modules)
Procedure
Step 1 Install a battery rack and batteries.
For details, see the battery installation guide delivered along with batteries.
----End

3.2.4 Installing Optional Components

3.2.4.1 Installing Antiseismic Kits

Install antiseismic kits only when the cabinet is ground-mounted.
Step 1 Mark mounting holes on the ground based on the marking-off templates.
Figure 3-45
Issue 05 (2018-01-08)
Before installing batteries, read through the battery safety precautions, obtain the delivered
battery installation guide, and install batteries as instructed.
Place the batteries in a correct way to prevent vibrations and shocks.
Install the batteries from the lower layer to the upper layer to prevent falling over due to
imbalance.
show the dimensions of antiseismic kit mounting holes.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
3 Installation
Figure 3-43