3.2.3 Installing Optional Components

3.2.3.1 Installing Antiseismic Kits

Install antiseismic kits only when the cabinet is floor-mounted.
Step 1 Determine the positions for installing the antiseismic kits. Mark mounting holes based on the
drawings.
Figure 3-25 Mounting holes (Unit of measurement: mm)
Step 2 Drill holes for installing expansion bolts, and install expansion bolts.
Step 3 Open the front door and remove support baffle plates on the front of the cabinets, as shown in
Figure
Issue 06 (2020-01-10)
Figure 3-25
shows the hole dimensions.
3-26. Remove the rear covers.