Procedure
Step 1 Install a battery rack and batteries.
For details, see the battery installation guide delivered along with batteries.
----End
3.2.4 Installing Optional Components
3.2.4.1 Installing an IP21 Component
Procedure
Step 1 Install leveling feet at the bottom of the IP21 component, with two long feet on
the front and two short feet at the rear.
Figure 3-36 Installing leveling feet
Step 2 Secure the IP21 component to the top of each cabinet.
Issue 17 (2023-07-10)
NO TE
● Refer to the "front" and "back" silk screens on the surface of the IP21 component.
● Select the mounting holes for leveling feet based on the cabinet width onsite.
Copyright © Huawei Digital Power Technologies Co., Ltd.
3 Installation
102