4. Go online and select the devices whose firmware you wish to update.
5. Click "Firmware update" to download the new firmware to the devices. To do so, you
6. When the firmware update is complete, switch the 24 V power supply off and on again.
7.4.5.4

Download project to target system

Once all the changes required for upgrading your project have been made, you must
download the project to the SIMOTION D4x5-2.
Requirement
The firmware required is located on the CompactFlash card; for information, refer to the
section titled Firmware update via CompactFlash card (Page 339).
You have recompiled the project and checked it for consistency. See Section Save project,
compile and check consistency (Page 330).
Procedure
1. Save the project.
2. Click "Connect to selected target systems" to establish a connection to the target system.
3. Execute "Download project to target system" and then "Copy RAM to ROM" to download
4. Because of the automatic follow-up configuration in the SINAMICS Integrated drive, you
5. Save the project.
SIMOTION D4x5-2
Commissioning and Hardware Installation Manual, 02/2012
The list displays the current firmware version of the devices.
must select all components whose firmware is to be updated.
The device is now ready for operation.
Note
The SINAMICS components must be configured for a firmware update to take place. The
firmware cannot be updated if the components have not been configured.
You can also update the firmware via the expert list. See the
Commissioning Manual for a description of how to do this.
the upgraded project to the CompactFlash card as well.
must now execute "Load CPU / drive unit to PG".
Note
When upgrading SINAMICS drive units (e.g. SINAMICS Integrated) only the p
parameters (setting parameters) are loaded into the upgraded project. The r parameters
(monitoring parameters) are not loaded. The r parameters in the drive unit are derived or
calculated from an automatic subsequent parameterization and must therefore be
uploaded to the project. To do this, execute "Load CPU/drive unit to PG". If the upload is
not performed, this can lead to inconsistencies in the drive parameterization dialog boxes.
Service and maintenance
7.4 Performing a firmware and project update
SINAMICS S120
341

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents