15.4
Powering On the System After Power
Centerplane Installation
1. Connect the AC power cords to the 4 kW dual
2. Connect all I/O cables referencing the cable label for proper identification.
3. Power on the AC0 and AC1 circuit breakers for all power supplies in the system.
4. Close the Sun Fire E25K/E20K system cabinet access doors.
5. Once the main SC is booted, start the domain(s) by typing:
sc% setkeyswitch -d domain_id
where domain_id is the domain letter A-R.
6. Execute one
command for each domain to be started.
setkeyswitch