4. Screw, 3.5x20
Torx T10
Unplug the Vibration Motor from the connector on the Main PCB.
Remove the Screw 3.5x20 (Torx T10) from the clamp then remove the clamp.
The Vibration Motor can now be lifted out of the detector chassis.
c.
Having removed the Vibration Motor, it can now be replaced, if required.
d.
Replace the Vibration Motor by reversing the steps to remove the Vibration Motor.
Figure 101: Vibration Motor Parts
Figure 102: Remove Vibration Motor