Loading Container Maintenance
7. Grease the roller at the grease point near it using general-purpose water resistant
grease.
8. Verify both rubber stoppers inside the tracks as they may be the cause of roller
failure. Always secure the roof before attempting any work. See
page
14.
1.6.4
Sliding Shoe Replacement Procedure
The container sliding shoe is made of teflon and should be checked on a daily basis.
Replace it as soon as thickness goes below ¼ inch.
To replace the sliding shoe:
1. Bring the bucket all the way up.
2. Use a ladder to install the loading bucket safety pins.
3. Perform the Lockout/Tagout procedure.
4. With the same ladder you use to install the safety pins, gain access to the sliding
shoe located in the rear of the bucket.
5. Remove the T-nuts and then the sliding shoe.