Generator Power Supply (Distribution Box) - Brainlab ExacTrac Planning Manual

With a varian truebeam linear accelerator
Table of Contents

Advertisement

APPENDIX
12.4.3

Generator Power Supply (Distribution Box)

Distribution Box Wiring Plan
You should provide a distribution box and must bring the power supply (5 lines: L1, L2, L3, N, PE)
to the generator. The cable should reach to the bottom of the generator plus 3 m for slack and the
cross section should not exceed 35 mm² (4AWG).
NOTE: A distribution box is not mandatory to operate the generator and patient positioning
system. However, for electrical safety reasons, applicable local regulations and work convenience,
a distribution box is strongly recommended.
The following image shows a sample of the wiring plan of a distribution box according to German
regulations. The design of this distribution box can be modified to accommodate local regulations:
Site Planning Manual Rev. 1.0 ExacTrac Ver. 6.x
L1
L2
L3
N
PE
S0
F1
F2
K1
0,03A
F3
L1 L2 L3 N PE X1
Figure 46
PE
N
Generator
111