FLOOR BOXES
Steps
Site Planning Manual Rev. 1.0 ExacTrac Ver. 6.x
Place first one half and then the second
half of the cardboard protection cover on
6
top of the wooden cover. Slide the
edges under the metal rim ①.
Use duct tape to connect the two halves
7
of the protection cover.
Pour quick drying concrete into the gap
8
around the floor box up to the finished
floor.
At least 10 mm of the rim of the aluminum cover must rest on stable
The ET floor box must be fixed to the pit with anchors (not supplied
filled up with
concrete
(concrete) floor.
by Brainlab) and be set in concrete.
Use mineral material only. Do not use chemical filling.
①
> 10mm
finished floor