Commissioning
7.2

Initial commissioning

During initial commissioning, follow the steps below:
Align transmitter and receiver
}
– Align transmitter
– Position tool
– Align receiver
Make adjustment during tool change
}
On the productive version: Configure braking ramp monitoring
}
Use the test piece to test the function of the safeguard
}
Prerequisites:
Transmitter and receiver must be installed correctly on the press brake (see
}
Installation [
An upper tool must be fitted to the right and left-hand edge of the press brake.
}
The supply voltage is present (PSSu K F FAU).
}
The individual steps are described in the following subsections.
Operating Manual PSENvip R, PSENvip R LR,PSENvip E
1003449-EN-06
71]) and electrically wired (see
CAUTION!
Have the protective equipment tested and certified before commis-
sioning for the first time!
Any machine safeguarded by the PSENvip must be tested and certified by
qualified personnel before it is placed on the market. A test report must be
generated and archived during initial commissioning.
Please note the guidelines given under "Safety".
Wiring [
77]).