A - Commissioning standalone 'Station' without PC
6
License
6 A - Commissioning standalone 'Station'
38 | 178
Building Technologies
Fire Safety
without PC
The procedure in this chapter is only valid for ↑ standalone 'Stations'.
In this commissioning variant, a ↑ 'Station' without a PC and a Cerberus-
Engineering-Tool are commissioned.
Prerequisites
●
The ↑ detector lines and C-NET devices are installed.
●
The acceptance test has been carried out for the detector lines.
●
The 'Station' is installed, but the batteries are not connected yet.
●
The cables for the detector lines and the mains supply have been inserted in
the 'Station', but not connected.
You will find additional information about the individual steps on the specified
pages.
Commissioning
1. If necessary, configure the power supply. Link [➙ 39]
2. Prepare the 'Station' for commissioning. Link [➙ 74]
3. Perform ↑ auto-configuration:
–
Auto-configure 'Station'. Link [➙ 75]
OR
–
Auto-configure detector lines individually. Link [➙ 76]
4. Adapt the auto-configuration in the ↑ Person Machine Interface, e.g.:
–
Changing customer texts. Link [➙ 39]
–
Set the ↑ parameter sets of the C-NET devices. Link [➙ 40]
5. Test the function of the ↑ 'Site' and remedy the problems, if any. Link [➙ 86]
6. Perform the completion tasks. Link [➙ 86]
A6V10210416_j_en_--